Logo
June 4, 2026 05:16
polatli besiktepe scaled

Kıranharmanı SPP

  • LV/MV Electrical Infrastructure and
  • IP Camera and Site Lighting
  • Design, Procurement, Built, Test,
  • Commissioning and TEDAŞ Acceptance

    Mechanical Installation: Pioneer EPC project, built with driven pile structures, grading and drainage works.
    Electrical Scope: DC string cabling, AC cabling to MV transformers, SCADA deployment.
    Safety Protocols: Early application of ISO 45001 procedures, PPE and site fencing.
    Commissioning: PR testing, inverter commissioning, TEDAŞ approval.
    Standards: IEC 62446, IEC 60364.

Project Information

6MW Solar Power Plant (SPP)
Polatlı/Kıranharmanı